Changing your plans after the agreement

Designs often change on site. If the change affects the work covered by the award, it usually needs to be dealt with formally before you carry it out.

Minor changes

Small changes within the scope of the award, such as a slightly different beam size in the same position, may be agreed by the surveyors with a short letter or record.

Material changes

Changes that alter how the work affects the neighbour usually need an addendum award. Examples:

  • Moving beams to a different part of the party wall
  • Deeper or different foundations
  • Adding a chimney breast removal that was not in the original scheme
  • Building onto the boundary where you had planned to set in

Work not covered by the original notice

If the change is a new type of work, such as an excavation where the original notice was only for the party wall, a fresh notice may be required before the surveyors can deal with it.

Why this matters

Work outside the award is not protected by it. If something goes wrong, you could face a dispute without the benefit of the agreed procedure.

Tips

  • Tell your surveyor as soon as a change is likely
  • Ask your engineer to flag anything touching the party wall
  • Allow time and budget for an addendum

Where this comes from in the Act

Links go to the official text of the Party Wall etc. Act 1996 on legislation.gov.uk.